Guide Origin: Community | ArcKit Version: [VERSION]
/arckit:oaa-adm-lite creates an O-AA ADM Lite document that maps the TOGAF ADM cycle onto agile sprints, drawing on Open Agile Architecture (O-AA, C208). It sets out a sprint plan from Sprint 0 (vision and stakeholders) to Sprint 4+ (governance and change), with the deliverables, go/no-go gate and O-AA axioms for each sprint. The sprint-to-phase mapping is an ArcKit convention over TOGAF ADM (C182); the O-AA standard itself does not define an ADM cycle. The command is part of the arckit-oaa overlay, which needs the core arckit plugin.
When to Use
| Use when any of these apply | Do not use when |
|---|---|
| The engagement has a hard timeline under 8 weeks for architecture and initial delivery | A full regulatory audit trail is required (use /arckit:adm-preliminary with the full ADM workflow) |
| The client works in an agile, sprint-driven culture | It is a multi-year transformation with 50+ stakeholder review gates |
| It is a first engagement and a rapid architecture vision is needed before scoping sprints | The baseline phase needs more than 4 weeks of current-state assessment |
| TOGAF alignment is required but quarterly boards and 200-page deliverables are not sustainable |
Inputs
| Artefact | Purpose |
|---|---|
Architecture principles (ARC-000-PRIN-v*.md) |
Recommended. Guiding principles, decision framework, technology standards. If missing, the command warns you to run /arckit:principles first |
ADM Preliminary / Architecture Vision (ARC-<id>-ADMP-v*.md) |
Recommended. Existing scope, drivers and constraints. If missing, Sprint 0 establishes the vision from scratch |
Stakeholder analysis (ARC-<id>-STKE-v*.md) |
Recommended. Roles, drivers, goals and concerns for the Sprint 0 stakeholder map |
Requirements (ARC-<id>-REQ-v*.md) |
Recommended. Business requirements and NFR targets for the Sprint 0 success criteria |
Project external documents (projects/<id>/external/) |
Read if present. Vision documents, strategic plans, enterprise architecture mandates |
Enterprise standards (projects/000-global/external/) |
Read if present. Architecture vision statements, transformation plans, cross-project alignment documents |
Command
/arckit:oaa-adm-lite <project ID or name>
Output: projects/<id>/ARC-<id>-OAAL-v1.0.md
If the named project does not exist, the command creates it. If an OAAL document already exists, it writes a new version (v2.0) instead of overwriting. Organisation-specific values (organisation_name, project_issue_prefix, safety_checklist_id, references_dir) come from the arckit-oaa plugin configuration; empty values fall back to placeholders such as [PENDING — organisation].
Sprint Map
| Sprint | TOGAF Phases | Focus | Duration | Key Output |
|---|---|---|---|---|
| Sprint 0 | ADM-P + A | Vision + Stakeholders | 1 week | vision.yaml |
| Sprint 1 | ADM-B + C (part) | Business + Data Architecture | 2 weeks | business-architecture.yaml, data-architecture.yaml |
| Sprint 2 | ADM-C (part) + D | Technology Architecture | 2 weeks | technology-architecture.yaml |
| Sprint 3 | ADM-E + F | Implementation Wave | 2 weeks | implementation-strategy.yaml |
| Sprint 4+ | ADM-G + H | Governance + Change | Ongoing | governance-report.yaml, change-request.yaml |
At the default sprint lengths, Sprint 0 to Sprint 3 take 7 weeks, inside the 4-8 week engagement window the approach is designed for. Sprint 0 names the high-level business capabilities in scope as part of the vision (TOGAF Phase A); Sprint 1 develops the baseline and target business capability map, which TOGAF places in Phase B.
The document cites the published O-AA axioms it applies by number and name: 1 (Customer Experience Focus), 3 (Rapid Feedback Loops), 5 (Value Stream Alignment), 6 (Autonomous Cross-Functional Teams), 7 (Authority, Responsibility, and Accountability Distribution), 10 (Simple Common Operating Principles), 14 (Bias for Change) and 15 (Project to Product Shift). It does not quote axiom text that cannot be checked against C208.
Deliverable Snapshot
| Section | Contents |
|---|---|
| Document Control | Document ID, owner, status, classification; review cycle per sprint |
| Trigger Guidance | When to use ADM Lite and when to use the full ADM instead |
| Sprint Map | Sprint-to-ADM-phase table with duration and key output |
| Sprint 0: Vision + Stakeholders (ADM-P + A) | Axiom alignment, activities, high-level capabilities in scope, vision.yaml structure (scope, constraints, stakeholders, success criteria, regulatory controls, risks), stakeholder-map.md, go/no-go gate |
| Sprint 1: Business + Data Architecture (ADM-B + C partial) | Baseline and target business capability map with gaps (business-architecture.yaml), value streams with SLAs, data assets and data flows with compliance controls, application components |
| Sprint 2: Technology Architecture (ADM-C continuation + D) | Technology standards, infrastructure and network topology, monitoring stack, compliance validation, architecture freeze |
| Sprint 3: Implementation Wave (ADM-E + F) | Work packages, migration waves and strategy with rollback trigger, risk register |
| Sprint 4+: Continuous Governance (ADM-G + H) | governance-report.yaml, governance cadence, change requests through /arckit:architecture-change |
| Sprint Artefact Traceability | Primary and secondary artefact for each sprint |
| Paperclip Integration | Issues per sprint, work package, compliance item and phase gate; issue naming convention |
| Comparison: Full ADM vs ADM Lite | What the lighter cadence trades away against the full ADM |
| External References | Document Register (C208 with URL and verification date), citations |
Review Checklist
- Every TOGAF ADM phase maps to a named sprint, or is recorded as deliberately out of scope.
- Sprint duration and engagement window agree with the sprint table.
- Each sprint has a deliverable and a sprint-level acceptance criterion, not just a theme.
- The document states what the lighter cadence gives up and does not claim to be an audit trail.
- Governance and change handling sit in a sprint or are handed to
/arckit:agile-governance. - The plan traces to the principles, and to the ADM Preliminary, stakeholder analysis and requirements where they exist.
- Run
/arckit:healthafter the build to catch stale or orphaned artefacts.
Next Steps
/arckit:product-architecture- Design product-centric architecture for the target product./arckit:agile-strategy- Plan dual transformation with the agile strategy canvas./arckit:agile-security- Embed security into the sprint rhythm./arckit:agile-governance- Establish governance cadence for the programme.